DESIGN AND RECLAMATION AT AYER MERBAU – PHASE 1 PART 2, JURONG ISLAND

Client :
Samsung C&T Corporation Ltd
Location :
Jurong Island, Singapore
Existing Revetment Removal :
32,000 m3
New Shore Protection rock Works :
45,000 m3
Supply & Lay Geofabric :
106,102 m2
Sand Trimming Works :
163,349 m3
Placing of Sand Bags :
13,000 pcs.
Construction Period :
July 2011 to December 2012 (18 months)

Description of project

Scope : Removal of Existing Revetment and Construction of New Sore Protection