PROVISION OF PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF COASTAL PROTECTION IMPROVEMENT AT KERTIH PORT SDN. BHD., KERTIH, MALAYSIA

Client :
Kertih Port Sdn. Bhd.
Location :
Kuala Terengganu, Malaysia
Sheet Pile Works :
180,000 m2
Rock Revetment Works :
10,000 m3
Geofabric Works :
18,000 m2
C40 Reinforced Concrete Works :
620 m3
Reinforced Works :
Nominal Diameter 16m - 0.2 ton
Nominal Diameter 12m - 13 ton
Nominal Diameter 10m - 2.5 ton
Lean Concrete Thickness 50mm Works :
20 m3
Sealant Works :
600 m3
Sand Backfilling for Repairing Works
440 m3
Construction Period :
June 2015 - December 2015 (6 months)

Description of project

Scope : Sheet Piling, Rock Revetment, Geofabric and C40 Reinforced Concrete, Lean Concrete Thickness 50mm., Sealant and Sand Backfilling for Repairing Works.