SHUQAIQ PHASE 2, INDEPENDENT WATER AND POWER PROJECT, KINGDOM OF SAUDI ARABIA

Client :
Shuqaiq Water and Electricity Company (SQWEC)
Main Contractor :
Mitsubishi Heavy Industries (MHI)
Location :
Shuqaiq, Kingdom of Saudi Arabia
Rock Works :
180,000 m3
Dredging Works :
700,000 m3
Geofabric Works :
55,000 m3
Reclamation Works :
120,000 m3
Excavation Works :
150,000 m3
Sand Bas Placing :
3100 nos.
Construction Period :
January 2008 - December 2009 (24 months)

Description of project

YTC’s scope of work was dredging and construction of seawater intake stilling Basin, Rockworks for Seawater outfall, Shore Protection and Dredging works for construction of temporary jetty. YTC was able to complete the project on time and within budget despite a very tight project schedule.